Scope



The capital improvement project will touch each building in the district to comply with state codes and to provide our students with the best and healthiest learning environment possible. Some areas of buildings are original to their construction and maintenance is now required to bring them up to code.
 
Kingsford Park ElementaryKingsford Park Elementary School
  • Life safety system upgrades
  • Replacement of Roof System
  • Replace domestic water system and associated fixtures
  • Replace interior floor finishes
  • Masonry restoration and reconstruction

 
Fitzhugh Park ElementaryFitzhugh Park Elementary School
  • Life safety system upgrades
  • Replacement of Roof System
  • Replace domestic water system and associated fixtures
  • Replace interior floor finishes
  • Masonry restoration and reconstruction

 
Minetto ElementaryMinetto Elementary School
  • Life safety system upgrades
  • Replacement of Roof System
  • Replace domestic water system and associated fixtures
  • Replace interior floor finishes
  • Masonry restoration and reconstruction
  • Replacement of exterior wall panels
  • Replacement of exterior windows
  • Replacement of interior doors and hardware for security
  • Exterior site reconstruction
  • Classroom reconstruction


Oswego Middle SchoolOswego Middle School
  • Life safety system upgrade
  • Windows, doors, hardware replacement
  • Mechanical system replacement and upgrades
  • Replace of interior floor finishes
  • Electrical system upgrades
  • Raise corridor walls to meet code
  • Replace domestic water system and associated fixtures
  • Replace lockers
  • Exterior site reconstruction


Charles E. Riley ElementaryCharles E. Riley Elementary School
  • Life safety system upgrades
  • Replacement of interior classroom wall system including cubbies/lockers
  • Replacement of interior doors and hardware for security
  • Replace domestic water system and associated fixtures
  • Mechanical system upgrades

 
Frederick Leighton ElementaryFrederick Leighton Elementary School
  • Life safety system upgrades
  • Replacement of interior floor finishes
  • Reconstruction of athletic wing – classrooms and locker rooms
  • Replacement of interior doors and hardware for security
  • Replace domestic water system and associated fixtures
  • Exterior campus-wide site reconstruction
  • Lobby reconstruction


Oswego High SchoolOswego High School
  • Life safety system upgrades
  • Mechanical system replacement and upgrades
  • Replace domestic water system and associated fixtures
  • Locker room reconstruction
  • Music suite renovations
  • Asbestos floor tile removal
  • Exterior campus-wide site reconstruction



The Oswego High School and Leighton campuses will see significant exterior reconstruction to improve and modernize the surrounding field areas. The capital improvement project calls for the installation of a new, multi-purpose Buccaneers field and parking lot in the south-west corner, new softball and baseball fields north of Leighton with a practice field for the Marching Buccaneers.
An additional 99 parking spots will also be added to the lot adjacent to the tennis courts, between OHS and Leighton.